HS HWASUNG CO., LTD. Yeongcheon-Singyeongju double-track railway works contract raised to KRW 47.2 billion

HS HWASUNG CO., LTD.· Single Sales/Supply ContractAmended

AI summary · Not investment advice

HS HWASUNG CO., LTD.'s share of a Yeongcheon-Singyeongju double-track railway roadbed contract signed in 2015 rose from KRW 46.1 billion to KRW 47.2 billion.

Contract amount

KRW 47.2 billion

11.2% of recent revenue · changed from KRW 46.1 billion · including VAT

Key facts

Counterparty
A state railway agency
Contract details
Jungang Line Yeongcheon-Singyeongju double-track railway, section 1 roadbed constructionConstruction order
% of revenue
11.2%Previously 11.0%
Contract period
Jun 1, 2015 – Dec 31, 2026
Recent revenue
KRW 420.7 billion2014 consolidated
Supply region
Yeongcheon, North Gyeongsang Province
Contract date
Jun 1, 2015
Payment terms
Paid as work is completedNo down payment or advance

Commentary

AI commentary · Not investment advice

What happened

The contract amount for section 1 roadbed works on the Jungang Line Yeongcheon-Singyeongju double-track railway, ordered by a state railway agency, has increased. Several companies share the project, and HS Hwasung's share is 25.08% of the total KRW 188.2 billion, up from 25.02%. Its share rose from KRW 46.1 billion to KRW 47.2 billion, including VAT. The work is in Yeongcheon, North Gyeongsang Province.

In the company's terms

The new amount equals 11.2% of recent revenue (KRW 420.7 billion, 2014 consolidated), up from 11.0% before. The company said the construction period and amount may change again as work progresses.

Earlier Single Sales/Supply Contract filings from this company

Filings of the same type
FiledCounterpartyContract amount% of revenue
26.11.06Anyang-dong 30-11 Street Housing Redevelopment AssociationKRW 92.4 billion10.2%

Comments

No comments yet