KC Cottrell Co., Ltd. KRW 6.1 billion bottom ash handling upgrade order for Samcheok Unit 2 from Korea Southern Power

KC Cottrell Co., Ltd.· Single Sales/Supply Contract

AI summary · Not investment advice

KC Cottrell Co., Ltd. signed a KRW 6.1 billion contract with Korea Southern Power to expand bottom ash handling for Samcheok Unit 2's boiler (3.18% of recent revenue).

Contract amount

KRW 6.1 billion

3.18% of recent revenue

Key facts

Counterparty
Korea Southern Power
Contract details
Purchase with installation to expand bottom ash handling capacity for the Samcheok Unit 2 boilerConstruction order
% of revenue
3.18%
Contract period
Oct 7, 2026 – Apr 30, 2027
Recent revenue
KRW 192.9 billion2025 consolidated
Contract date
Oct 7, 2026
Supply region
Samcheok
Payment terms
Equipment paid in cash after delivery; construction paid monthly in cash by progressDown payment or advance included

Commentary

AI commentary · Not investment advice

What happened

KC Cottrell signed a contract with Korea Southern Power for boiler equipment at Samcheok Unit 2. The work is to purchase and install equipment that increases capacity to handle ash left at the bottom of the boiler (bottom ash). The contract is worth KRW 6.1 billion, excluding VAT.

In the company's terms

The contract equals 3.18% of recent annual revenue (KRW 192.9 billion). Revenue is on a 2025 consolidated basis.

What changes for shareholders

The contract runs until 2027.04.30. Equipment is paid in cash after delivery, and construction is paid in cash each month based on progress. The company said the amount and period may change as work proceeds.